Description
9907-162 启动蒸汽系统,向汽轮机供应蒸汽
汽轮机是一种将蒸汽的热能转换为机械能的旋转式动力机械,9907-162 是现代火力发电厂中应用最广泛的原动机。以下是一些操作汽轮机的基本步骤:
1. 启动前检查:在启动汽轮机之前,需要进行一系列的检查,包括检查润滑油系统、冷却水系统、蒸汽系统、控制系统等是否正常。
2. 启动蒸汽系统:启动蒸汽系统,向汽轮机供应蒸汽。
3. 启动润滑油系统:启动润滑油系统,向汽轮机的轴承和齿轮供应润滑油。
4. 启动汽轮机:当蒸汽和润滑油系统正常运行后,可以启动汽轮机。在启动过程中,需要注意控制蒸汽流量和压力,以避免对汽轮机造成损坏。
5. 调节输出功率:根据需要,调节汽轮机的输出功率。可以通过调节蒸汽流量、压力和转速等参数来实现。
6. 监测运行状态:在汽轮机运行过程中,需要监测其运行状态,包括蒸汽压力、温度、转速、振动等参数。如果发现异常情况,需要及时采取措施进行处理。
7. 停机:当需要停机时,需要逐渐减少蒸汽流量和压力,直到汽轮机停止运转。在停机过程中,需要注意控制润滑油系统和冷却水系统的运行,以避免对设备造成损坏。
需要注意的是,9907-162 操作汽轮机需要专业的技术人员进行操作,并且需要严格遵守操作规程和安全规定,以确保设备的安全和正常运行。
9907-162 启动蒸汽系统,向汽轮机供应蒸汽
Steam turbine is a kind of rotary power machinery that converts the thermal energy of steam into mechanical energy. 9907-162 is the most widely used prime mover in modern thermal power plants. Here are some basic steps to operate a steam turbine:
1. Pre-start inspection: Before starting the steam turbine, a series of inspections need to be carried out, including checking whether the lubricating oil system, cooling water system, steam system, control system, etc., is normal.
2. Start the steam system: Start the steam system to supply steam to the turbine.
3. Start the lubricating oil system: Start the lubricating oil system to supply lubricating oil to the bearings and gears of the turbine.
4. Start the steam turbine: When the steam and lubricating oil system is running normally, the steam turbine can be started. During the start-up process, it is necessary to control the steam flow and pressure to avoid damage to the turbine.
5. Adjust the output power: adjust the output power of the turbine as required. It can be achieved by adjusting steam flow, pressure and speed parameters.
6. Monitoring operation status: During the operation of the steam turbine, it is necessary to monitor its operating status, including steam pressure, temperature, speed, vibration and other parameters. If an exception occurs, you need to take measures in time.
7. Shutdown: When it is necessary to stop, it is necessary to gradually reduce the steam flow and pressure until the turbine stops running. During the shutdown process, it is necessary to control the operation of the lubricating oil system and the cooling water system to avoid damage to the equipment.
It should be noted that the operation of the 9907-162 steam turbine requires professional and technical personnel to operate, and needs to strictly abide by the operating procedures and safety regulations to ensure the safety and normal operation of the equipment.